May 2010 The Drawing Room before Restoration |
May 2010 The drawing room before restoration |
May 2010 Structural Distress in Flooring leading to sweating of the floor |
Sept 2012 Careful removal of the sweated flooring to conduct investigations to understand the cause of structural distress |
Sept 2012 Investigation pits were dug to investigate the sweating of the floor |
October 2013 Careful hacking of the cement plaster |
October 2013 Cement plaster removed and masonry allowed to breathe |
January 2014 All cement plaster is removed and the masonry is ready for a the first coat of plaster |
February 2014 First coat of lime plaster applied and lime concrete floor consolidated |
March 2014 Thats how the first coat of coarse plaster looked when first applied |
July 2014 All cornices have been rebuilt in lime mortar after the second coat of finishing plaster has been laid and dried |
October 2014 Work begins in the drawing room as the scaffolding goes up |
October 2014 Finishing work in Lime Plaster for the haveli begins |
October 2014 The intricate fanlights are meticulously restored on site by the local carpenters |
November 2014 We are now ready to lay our flooring, the craftsmen are getting their levels right |
November 2014 And so we began laying the black and white chequered flooring to match the original |
December 2014 The room is beginning to take shape |
December 2014 The room begins to take shape |
December 2014 The fanlight is now fixed |
December 2014 The other fanlights are ready for installation |
January 2015: The textured local glass is now fixed |
January 2015: Piece by piece the grandeur is returning |
January 2015 Locally made handles adorn the restored historic doors |
January 2015 We inch closer to restoring its original glory |
May 2015: And we are ready to move in! |
May 2015: The light fittings add to the ambiance |
May 2015: We await the furniture now |
May 2015: Awaiting the furniture now |